Before a single fixture is ordered or a steel beam is fabricated, the design team wants to see exactly what the contractor plans to install. That is the job of a submittal. If you are asking what is a submittal in construction, this guide explains the types, who prepares and reviews them, how the process works and how submittals affect your schedule and your estimate.
Types of Construction Submittals
| Submittal Type | What It Shows | Examples |
|---|---|---|
| Shop drawings | Detailed drawings made by the fabricator or installer | Structural steel, rebar, ductwork, millwork, curtain wall |
| Product data | Manufacturer sheets showing model, size and performance | Light fixtures, HVAC units, plumbing fixtures, roofing |
| Samples | Physical pieces of the finish or material | Tile, paint colors, brick, carpet, hardware |
| Mock-ups | A built sample section for approval on site | Masonry panels, window and wall assemblies |
| Tests and certificates | Proof that materials meet required standards | Concrete mix designs, fire ratings, welder certifications |
| Closeout documents | Information the owner needs after completion | Warranties, O&M manuals, as-built drawings |
Who Prepares and Reviews Submittals?
- Subcontractors and suppliers prepare most submittals for their own work.
- The general contractor checks them against the plans and specifications, coordinates between trades and stamps them before sending them on.
- The architect or engineer reviews for design intent and returns them with a review stamp and comments.
- The owner may review finishes, colors and major equipment selections.
The Submittal Process Step by Step
Step 1: Build the Submittal Register
Go through every specification section and list each required submittal, its type and its due date. This list becomes the submittal log.
Step 2: Prepare the Package
The subcontractor or supplier assembles the shop drawings, data sheets or samples, clearly marking the exact model and options being proposed.
Step 3: Contractor Review
The general contractor checks dimensions, quantities and coordination with other trades, then stamps and forwards the package.
Step 4: Design Team Review
The architect or engineer reviews the submittal within the time set in the contract and returns it with a review action.
Step 5: Release, Revise or Resubmit
Approved items are released for ordering and fabrication. Items marked revise and resubmit go back through the cycle, which can delay the schedule.
Review Stamps and What They Mean
| Review Action | Meaning | Next Step |
|---|---|---|
| Approved / No exceptions taken | Meets the design intent | Order and install |
| Approved as noted | Accepted with comments | Proceed following the notes |
| Revise and resubmit | Changes needed before approval | Correct and send again |
| Rejected | Does not meet requirements | Propose a different product |
The Submittal Log
A submittal log tracks every item: specification section, description, responsible subcontractor, date sent, date returned, review action and current status. Many teams use project management software, but a well-kept spreadsheet works for smaller jobs. Reviewing the log weekly keeps late items from holding up procurement.
How Submittals Affect Your Estimate
- Specified products: price the exact manufacturers and models in the specifications, since substitutions may not be accepted.
- Long-lead items: account for price escalation and storage if materials must be ordered early.
- Engineering costs: delegated design items such as steel connections or fire sprinkler layouts require engineered shop drawings, which cost money.
- Samples and mock-ups: include material and labor for any mock-ups the specifications require.
- Administration time: preparing and tracking submittals is part of project management and general conditions.
These items are easy to miss on bid day. Our guides on how to bid a construction job and preparing a detailed estimate show where they fit, and the punch list guide covers the end of the same document trail.
Frequently Asked Questions
What is a submittal in construction?
A submittal is a document, sample or drawing the contractor sends to the architect or engineer to show exactly what will be installed, so they can confirm it meets the design before work starts.
What are the main types of submittals?
The main types are shop drawings, product data sheets, samples and mock-ups. Test reports, certificates, warranties and operation and maintenance manuals are also common.
How long does submittal review take?
Many specifications allow about 10 to 14 days for each review, but the exact time is set in the contract, usually in Division 01.
What does approved as noted mean?
It means the submittal is accepted with the reviewer’s comments, and the work can proceed as long as those notes are followed. A full resubmittal is usually not needed.
Who prepares construction submittals?
Subcontractors and suppliers usually prepare them, the general contractor reviews and stamps them, and the architect or engineer gives the final review.
Price the Specs Exactly as Written
Specifications decide which products you can use and what submittals you owe. Mega Estimating reads the specs, prices the specified products and lists long-lead and delegated-design items so nothing is missed. Mega Estimating is a U.S. construction estimating company that prepares quantity takeoffs and detailed cost estimates for residential, commercial and industrial contractors.