What is a submittal in construction - submittal types and review process

Before a single fixture is ordered or a steel beam is fabricated, the design team wants to see exactly what the contractor plans to install. That is the job of a submittal. If you are asking what is a submittal in construction, this guide explains the types, who prepares and reviews them, how the process works and how submittals affect your schedule and your estimate.

Short answer: A submittal is a shop drawing, product data sheet, sample or other document that the contractor sends to the architect or engineer for review before ordering or installing work. It proves the proposed product or method meets the plans and specifications. Requirements are usually listed in specification section 01 33 00, Submittal Procedures.

Types of Construction Submittals

Submittal TypeWhat It ShowsExamples
Shop drawingsDetailed drawings made by the fabricator or installerStructural steel, rebar, ductwork, millwork, curtain wall
Product dataManufacturer sheets showing model, size and performanceLight fixtures, HVAC units, plumbing fixtures, roofing
SamplesPhysical pieces of the finish or materialTile, paint colors, brick, carpet, hardware
Mock-upsA built sample section for approval on siteMasonry panels, window and wall assemblies
Tests and certificatesProof that materials meet required standardsConcrete mix designs, fire ratings, welder certifications
Closeout documentsInformation the owner needs after completionWarranties, O&M manuals, as-built drawings

Who Prepares and Reviews Submittals?

  • Subcontractors and suppliers prepare most submittals for their own work.
  • The general contractor checks them against the plans and specifications, coordinates between trades and stamps them before sending them on.
  • The architect or engineer reviews for design intent and returns them with a review stamp and comments.
  • The owner may review finishes, colors and major equipment selections.

The Submittal Process Step by Step

Step 1: Build the Submittal Register

Go through every specification section and list each required submittal, its type and its due date. This list becomes the submittal log.

Step 2: Prepare the Package

The subcontractor or supplier assembles the shop drawings, data sheets or samples, clearly marking the exact model and options being proposed.

Step 3: Contractor Review

The general contractor checks dimensions, quantities and coordination with other trades, then stamps and forwards the package.

Step 4: Design Team Review

The architect or engineer reviews the submittal within the time set in the contract and returns it with a review action.

Step 5: Release, Revise or Resubmit

Approved items are released for ordering and fabrication. Items marked revise and resubmit go back through the cycle, which can delay the schedule.

Scheduling tip: Submit long-lead items first. Switchgear, elevators, structural steel and custom windows can take months to arrive after approval.

Review Stamps and What They Mean

Review ActionMeaningNext Step
Approved / No exceptions takenMeets the design intentOrder and install
Approved as notedAccepted with commentsProceed following the notes
Revise and resubmitChanges needed before approvalCorrect and send again
RejectedDoes not meet requirementsPropose a different product

The Submittal Log

A submittal log tracks every item: specification section, description, responsible subcontractor, date sent, date returned, review action and current status. Many teams use project management software, but a well-kept spreadsheet works for smaller jobs. Reviewing the log weekly keeps late items from holding up procurement.

How Submittals Affect Your Estimate

  • Specified products: price the exact manufacturers and models in the specifications, since substitutions may not be accepted.
  • Long-lead items: account for price escalation and storage if materials must be ordered early.
  • Engineering costs: delegated design items such as steel connections or fire sprinkler layouts require engineered shop drawings, which cost money.
  • Samples and mock-ups: include material and labor for any mock-ups the specifications require.
  • Administration time: preparing and tracking submittals is part of project management and general conditions.

These items are easy to miss on bid day. Our guides on how to bid a construction job and preparing a detailed estimate show where they fit, and the punch list guide covers the end of the same document trail.

Frequently Asked Questions

What is a submittal in construction?

A submittal is a document, sample or drawing the contractor sends to the architect or engineer to show exactly what will be installed, so they can confirm it meets the design before work starts.

What are the main types of submittals?

The main types are shop drawings, product data sheets, samples and mock-ups. Test reports, certificates, warranties and operation and maintenance manuals are also common.

How long does submittal review take?

Many specifications allow about 10 to 14 days for each review, but the exact time is set in the contract, usually in Division 01.

What does approved as noted mean?

It means the submittal is accepted with the reviewer’s comments, and the work can proceed as long as those notes are followed. A full resubmittal is usually not needed.

Who prepares construction submittals?

Subcontractors and suppliers usually prepare them, the general contractor reviews and stamps them, and the architect or engineer gives the final review.

Price the Specs Exactly as Written

Specifications decide which products you can use and what submittals you owe. Mega Estimating reads the specs, prices the specified products and lists long-lead and delegated-design items so nothing is missed. Mega Estimating is a U.S. construction estimating company that prepares quantity takeoffs and detailed cost estimates for residential, commercial and industrial contractors.

Get 50% Off Your First Estimate

Leave a Reply

Your email address will not be published. Required fields are marked *

Mega Estimating logo

Let us help you get your project started

First estimate: 50% off MEGA / EST / 2026
Add plans or notes (optional)

Your drawings stay confidential. We never share your details with third parties.

Mega Estimating logo

Let us help you get your project started

First estimate: 50% off MEGA / EST / 2026
Add plans or notes (optional)

Your drawings stay confidential. We never share your details with third parties.