Change order in construction - process, pricing and examples

No construction project is built exactly as drawn. Owners change their minds, drawings miss details, and crews uncover conditions nobody expected. A change order in construction is the formal way to adjust the contract when that happens. Handled well, it protects both the owner’s budget and the contractor’s margin. Handled badly, it becomes the number one source of disputes on a job.

Short answer: A change order is a written, signed amendment to the construction contract that changes the scope of work, the contract price, the schedule or all three. It is priced from direct costs (labor, material, equipment and subcontracts) plus the overhead and profit markup allowed in the contract, and it should be agreed before the extra work begins.

Why Change Orders Happen

CauseExampleWho Usually Pays
Owner requestUpgraded finishes, extra rooms, added equipmentOwner
Design error or omissionMissing structural detail, clash between tradesOwner, who may recover from the designer
Unforeseen conditionsBuried rock, old foundations, rotted framingDepends on the contract’s differing site conditions clause
Code or authority requirementInspector requires added fire protectionDepends on contract and cause
Value engineeringContractor proposes a cheaper equal productCredit to owner, often shared

The Change Order Process Step by Step

Step 1: Identify the Change

A field issue, RFI response, revised drawing or owner request shows that the work differs from the contract documents.

Step 2: Give Written Notice

Notify the owner or architect in writing within the notice period in the contract. Late notice is one of the most common reasons claims are denied.

Step 3: Prepare the Change Order Request

Describe the change, attach drawings or photos, and price the cost and schedule impact with a clear breakdown.

Step 4: Review and Negotiate

The owner and design team review the request, ask questions and agree on scope, price and time.

Step 5: Sign and Proceed

Both parties sign the change order, often on a standard form such as the AIA G701, and the contract sum and schedule are updated. The new amount is then billed through the schedule of values.

Golden rule: Get it in writing before the work starts. Verbal approvals in the field are hard to prove at the end of the job.

How to Price a Change Order

  • Labor: hours by trade times the burdened labor rate. See how to estimate labor costs.
  • Materials: measured quantities times current prices, including waste, freight and tax.
  • Equipment: rental or owned equipment time needed for the change.
  • Subcontractors: sub quotes plus the markup the contract allows on sub work.
  • Overhead and profit: the percentage set in the contract, commonly applied to the direct cost.
  • Time: extra days and the general conditions cost of extending the schedule.
  • Credits: any deleted work, priced as a deduction.

Worked Example: Adding Two Interior Doors

ItemCalculationAmount
Materials2 door assemblies, frames, hardware$1,400
Labor16 hours x $65 burdened rate$1,040
Direct cost subtotal$2,440
Overhead and profit15% of $2,440 (as set in the contract)$366
Change order total$2,806
ScheduleAdded time to frame, hang and finish+1 working day

Markup percentages vary by contract, so always use the rates written in your agreement rather than a rule of thumb.

Change Order vs Construction Change Directive

Sometimes work must continue before the price is agreed, for example to avoid delaying the critical path. In that case the owner may issue a construction change directive, such as an AIA G714, ordering the work to proceed. The contractor tracks actual costs, often on time and material tickets, and the final amount is settled later and converted into a change order.

Common Change Order Mistakes

  • Missing the notice deadline in the contract.
  • Starting work on a verbal OK without a signed change.
  • Forgetting time: pricing cost but not schedule impact.
  • Vague descriptions that lead to arguments about what was included.
  • No backup: missing photos, daily logs and time sheets. A good site diary solves this.

Frequently Asked Questions

What is a change order in construction?

A change order is a written agreement between the owner and contractor that changes the contract scope, price, schedule or all three after the contract is signed.

Who can request a change order?

The owner, architect, engineer or contractor can start one. Changes often come from owner requests, design errors or omissions, and unforeseen site conditions.

How do you price a change order?

Add direct costs for labor, materials, equipment and subcontracts, then apply the overhead and profit markup allowed in the contract, plus any bond and schedule costs.

What is the difference between a change order and a change directive?

A change order is agreed and signed by both parties. A construction change directive orders the work to proceed before price or time are agreed, with the amount settled later.

Can a contractor refuse a change order?

Most contracts require the contractor to perform changed work within the general scope, but the contractor is entitled to fair adjustment of price and time as the contract allows.

Price Change Orders Fast and Accurately

Change orders need quick, defensible numbers. Mega Estimating measures the changed scope from revised drawings and prices labor, material and markup so you can submit change order requests with confidence. Mega Estimating is a U.S. construction estimating company that prepares quantity takeoffs and detailed cost estimates for residential, commercial and industrial contractors.

Get 50% Off Your First Estimate

Leave a Reply

Your email address will not be published. Required fields are marked *

Mega Estimating logo

Let us help you get your project started

First estimate: 50% off MEGA / EST / 2026
Add plans or notes (optional)

Your drawings stay confidential. We never share your details with third parties.

Mega Estimating logo

Let us help you get your project started

First estimate: 50% off MEGA / EST / 2026
Add plans or notes (optional)

Your drawings stay confidential. We never share your details with third parties.